Gallery North

Project — Commercial

Gallery North

Oslo, Norway

Project dossier

Client
Gallery North AS
Location
Oslo, Norway
Industry
Commercial
Scope
Architectural joinery package: oak wall panelling, metal-mesh ceiling rafts, laminated glass partitions
Scale
Commercial gallery and offices, 4,200 m²
Status
Delivered 2026
Delivery timeline
RFQ to final drop: 24 weeks
Cost band
USD 860K–1.1M joinery package
Sample data

Designed by

Nordkap Arkitektur

Procured by

Bygg Partner Procurement

Owner / operator

Gallery North AS

Overcoming challenges

The brief, and how we landed it

The challenge

The main contractor's programme gave the joinery package a sequence of 11 just-in-time drops — material arriving early had nowhere to be stored, and late material idled a whole trade crew. The architect's oak veneer spec was a European-sourced product at a price and lead time the budget could not carry. Winter shipping to Oslo demanded weatherproof crating and heated quay handling.

How we delivered

We sourced and qualified an equivalent veneer, running side-by-side sample panels for the architect's approval against the original. All 11 drops were produced, cut-to-size and packed as zone-labelled kits matched to the contractor's sequence, shipped on a rolling schedule from our buffer stock. Glass and mesh panels shipped in weatherproof crates with handling instructions accepted by the Oslo terminal.

Scope of supply

What left our loading dock

Supply list

  • Cut-to-size oak wall panelling, 2,900 m²
  • Metal-mesh ceiling rafts, framed and numbered
  • Laminated glass partitions, 46 panels
  • 11 just-in-time drops as zone-labelled kits
  • Weatherproof crating with terminal-accepted handling instructions

Materials used

  • Oak Veneer
  • Metal Mesh
  • Glass

Value engineering on this project

The qualified veneer equivalent landed 33% below the specified European material while passing the architect's side-by-side panel review. Nesting all cut-to-size panels in our CNC programming raised board yield from 71% to 86%, funding the buffer-stock programme at no extra cost. Zone-labelled kit packing let the contractor's crew install straight from the crate, removing their quoted sorting labour.